Scope of Work
- Containerized liquid-cooling system installation for a 1.2 MW mining site running 192 miners
- Cold-plate and indirect hydro cooling loops, sized from 32 kW cabinets up to MW-class containers
- Concrete pads, equipment set and structural anchoring
- Electrical cabin tie-in and power interconnect coordination
- Dry cooler, CDU, pump skid and coolant piping integration
- Miner installation, cabling and PDU distribution
- System fill, leak check, flow balancing and commissioning
Small mining sites are built against the power interconnect date, not the construction calendar. Modular liquid-cooling containers let a farm scale in steps, and running the civil, mechanical and electrical scopes together kept each module ready when its power was.